Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Introduction

The schedules page allows you to specify one or more schedules that control when the rule is active or inactive. The system will check each configured schedule and if it finds at least one matching schedule then the rule will be active, otherwise it will be ignored. Configured schedules can also be disabled, which leaves them in place but they are no longer considered when the rule checks the schedule list.

Panel
borderColorsilver
borderWidth1

On this page:

Table of Contents
maxLevel3
indent16px

Adding and Removing Schedules

Add a Schedule

  1. Select the Edit button to put the rule into Edit mode. The Add Schedule button will become active.

    Image Added

  2. Select the Add Schedule button and complete the details for the required event / schedule.

    Image Added

  3. Select Save once complete.

Remove a Schedule

  1. Select the Edit button to put the rule into Edit mode. The Add Schedule and Delete Schedule buttons will become active.

  2. Select the schedule you want to remove the list and select the Delete Schedule button.

    Image Added

  3. Select Save once complete.

Schedule Configuration

Schedule Name: the name of the event you are scheduling.

Description: a description of the event/task.

Begin/End Date: the day the scheduled event(s) will start, and the day they will end.

Start/Finish Time: the time the scheduled event(s) will start, and the time they will end.

Operation:

Inside - the event takes place inside of the scheduled time slot.

Outside - the event takes place outside of the scheduled time slot.

Repeat: whether you want to repeat the scheduled task, and how often.

Once - the schedule will only be active once between the dates and times specified. This is not suitable for long running tasks such as rules.

Daily - the schedule is active daily between the dates and times specified.

Weekly - if this option is selected you must select the relevant days of the weeks. The schedule will be active on these week days between the dates and times specified.

Monthly - if this option is selected you must select the days of the month. The schedule will be active on these days of the month between the dates and times specified.

Enabled: select this to make the schedule active. Disabled schedules will be ignored which is the equivalent of not having a schedule.


Filter by label (Content by label)
showLabelsfalse
max10
cqllabel = "witness-4"